Last updated: 2026-09-01 · 4 min read
What Should You Verify at T2 — and How Is It Different from T1?
T2 (the second mold trial) is the verification that the T1 corrections worked and the process is repeatable. While T1 is a discovery trial — establishing the process window, identifying defects, and generating the initial dimensional report — T2 is a confirmation trial that runs the documented T1 process settings and measures whether the parts are within tolerance, the cycle time matches the quotation, and the mold operates reliably over a 50–200 shot run. If T1 found the process, T2 proves it.
Flash — Thin excess material that escapes between the mold parting line or around ejector pins. Cause: insufficient clamp force, worn parting line, excessive injection pressure, or contaminated mold surface. Flash thickness: 0.02–0.1mm. Requires secondary trimming to remove. See also related guide.
Key Facts